Developing a custom lithium battery pack involves several stages, from defining technical requirements to engineering design, prototype manufacturing, testing, and mass production.
For OEM and ODM projects, the development timeline depends on battery specifications, cell selection, Battery Management System (BMS) requirements, enclosure design, component availability, and certification requirements.
Applications such as electric bicycles, AGVs, AMRs, service robots, industrial equipment, and energy storage systems have different electrical and mechanical requirements. Each project requires evaluation before production planning.
Understanding the custom battery pack development timeline helps equipment manufacturers coordinate product development, prototype evaluation, component procurement, and production schedules.
This article explains the main stages of custom lithium battery pack development and the factors that influence each stage.

1. Stage One: Define Battery Pack Requirements
The development process begins with confirming the battery specifications and equipment requirements.
Before designing a custom lithium battery pack, the manufacturer needs to understand the equipment’s electrical load, installation conditions, and operating environment.
Elektrische Anforderungen
OEM customers should provide:
- Nominal battery voltage
- Required capacity (Ah or Wh)
- Charging voltage and current
- Kontinuierlicher Entladestrom
- Peak discharge current and duration
- Betriebstemperatur
- Expected operating duty cycle
For example, an AGV battery project may require a 48V-class battery with a specified capacity, continuous discharge current, and peak current during acceleration.
These parameters determine the battery cell configuration and BMS electrical requirements.
Mechanical Requirements
The battery must fit within the available installation space.
Customers should provide:
- Maximum length, width, and height
- Battery compartment drawings
- Installation orientation
- Mounting positions
- Connector locations
- Cable routing requirements
- Enclosure material requirements
- Environmental protection requirements
Mechanical drawings in STEP, STP, or 2D PDF format can be used for design evaluation.
Communication and BMS Requirements
Some battery applications require communication between the battery and equipment controller.
Possible interfaces include:
- CAN
- UART
- RS485
Customers should also confirm whether the system requires SOC reporting, SOH reporting, temperature monitoring, fault information, or customized protection functions.
Stage Output: Confirmed battery requirements and initial technical specifications.
2. Stage Two: Technical Feasibility and Battery Design
After receiving the technical requirements, the battery manufacturer evaluates the proposed battery configuration.
This stage includes cell selection, electrical design, BMS evaluation, enclosure planning, and component selection.
Auswahl der Batteriezellen
Battery cells are selected according to the required voltage, capacity, discharge current, operating temperature, and mechanical dimensions.
Common battery chemistries include:
Ternary Lithium-Ion Batteries
Ternary lithium-ion cells, including nickel manganese cobalt (NMC) chemistry, are used in electric mobility, robotics, and portable equipment applications.
LiFePO4-Batterien
LiFePO4 cells are used in industrial equipment, AGVs, AMRs, and energy storage systems.
Cell selection should follow the technical specifications of the selected manufacturer and model.
Series and Parallel Configuration
The battery pack configuration is determined by the required nominal voltage and capacity.
Zum Beispiel:
| Batteriekonfiguration | Nennspannung | Application Example |
|---|---|---|
| 10S Ternary Lithium-Ion | 36V | Electric bicycle |
| 13S Ternary Lithium-Ion | 46.8V | 48V-class electric mobility |
| 14S Ternary Lithium-Ion | 50.4V | Equipment requiring this voltage range |
| 8S LiFePO4 | 25.6V | 24V-class industrial equipment |
| 16S LiFePO4 | 51.2V | Industrial equipment and energy storage |
The voltage examples are based on typical cell nominal voltages. Actual configurations depend on the selected cell specifications.
BMS Design and Evaluation
The BMS is selected or customized according to the electrical and communication requirements.
Design considerations may include:
- Überwachung der Zellspannung
- Charging and discharging protection
- Überstrom- und Kurzschlussschutz
- Überwachung der Temperatur
- Zellausgleich
- CAN, UART, or RS485 communication
- SOC and SOH reporting
- Connector and wiring configuration
If a project requires a customized BMS PCB or firmware development, the engineering scope should be confirmed before prototype production.
Mechanical and Enclosure Design
Battery enclosure design may include:
- Zellanordnung
- Internal insulation
- BMS installation position
- Wohnungsstruktur
- Connector layout
- Mounting brackets
- Wasserdichte Abdichtung
- Wärmeableitung
The design should account for manufacturing processes, assembly requirements, and the equipment’s installation conditions.
Stage Output: Proposed electrical configuration, BMS solution, mechanical design, and preliminary bill of materials (BOM).
3. Stage Three: Engineering Review and Design Confirmation
Before prototype manufacturing, the proposed battery design should be reviewed against the customer’s technical requirements.
This stage may include coordination between the battery manufacturer and the customer’s engineering team.
Electrical Design Review
The review covers:
- Battery voltage and capacity
- Zellkonfiguration
- Kontinuierlicher Entladestrom
- Peak current capability
- Ladevorgaben
- BMS protection functions
- Connector specifications
Mechanical Design Review
The mechanical review covers:
- External dimensions
- Installation orientation
- Mounting positions
- Connector locations
- Cable lengths
- Gehäusestruktur
- Assembly requirements
Project Cost Confirmation
The manufacturer may also confirm development-related costs, including:
- Prototypenfertigung
- Customized BMS development
- Mechanical tooling
- Special connectors
- Certification testing
- Production tooling
Any design changes should be documented before sample manufacturing.
Stage Output: Approved prototype specifications, drawings, and development scope.
4. Stage Four: Custom Battery Pack Prototyping
Prototype production is an important stage of custom battery pack development.
Engineering samples allow the manufacturer and customer to evaluate the battery’s electrical performance, mechanical compatibility, and system integration.
Prototype Material Preparation
Materials may include:
- Batteriezellen
- BMS boards
- Nickel strips or busbars
- Cell holders
- Insulation materials
- Steckverbinder
- Wiring harnesses
- Battery enclosures
Material preparation depends on component specifications, stock availability, and purchasing requirements.
Battery Pack Assembly
Prototype assembly may involve:
- Prüfung von Batteriezellen
- Zellanordnung
- Electrical connection and welding
- Insulation installation
- BMS assembly and connection
- Wiring and connector installation
- Enclosure assembly
- Initial electrical inspection
The assembly method depends on the battery cell format and mechanical structure.
Prototype Inspection
Before samples are submitted for customer evaluation, inspection may include:
- Batteriespannung
- Cell group voltage
- Connection polarity
- Insulation
- BMS protection functions
- Charging and discharging operation
- Kommunikationsfunktionen
- External dimensions
The testing scope should follow the approved prototype specifications.
Stage Output: Engineering battery pack samples for internal and customer evaluation.
5. Stage Five: Battery Pack Testing and Validation
After prototype assembly, the battery pack must be evaluated against the project requirements.
Testing helps identify electrical, mechanical, thermal, and communication issues before production approval.
Electrical Testing
Electrical testing may include:
- Prüfung der Kapazität
- Charging verification
- Continuous discharge testing
- Peak current testing
- Schutz vor Überladung
- Schutz vor Überentladung
- Überstromschutz
- Kurzschlussschutz
Thermische Prüfung
Temperature-related testing may include:
- Temperature rise during discharge
- High-temperature operation
- Low-temperature discharge
- Charging temperature protection
- BMS temperature monitoring
Test conditions should follow the selected cell specifications and project requirements.
Mechanical Testing
Depending on the application, mechanical evaluation may include:
- Dimension inspection
- Installation fit testing
- Vibrationsprüfung
- Connector mating verification
- Enclosure inspection
- Mounting structure verification
Communication Testing
For battery packs equipped with CAN, UART, or RS485 communication, testing may cover:
- Data transmission
- SOC reporting
- Voltage and current reporting
- Temperature information
- Fehlerinformationen
- Communication protocol compatibility
Communication functions must be verified according to the agreed interface specifications.
Stage Output: Prototype test results and technical evaluation records.
6. Stage Six: Customer Sample Evaluation and Approval
After receiving the prototype, the customer evaluates the battery in the actual equipment.
This stage is important because laboratory testing alone may not represent the complete equipment operating conditions.
Equipment Integration Testing
The customer may evaluate:
- Battery installation
- Equipment startup
- Motorbetrieb
- Continuous power demand
- Peak current behavior
- Charging compatibility
- Communication with the equipment controller
- Operating runtime
For example, an AMR manufacturer may test the battery during repeated acceleration, navigation, loading, and charging cycles.
Design Modifications
If the prototype does not meet the agreed requirements, modifications may be necessary.
Common changes include:
- BMS parameter adjustments
- Connector replacement
- Cable length modifications
- Enclosure dimension changes
- Cell configuration adjustments
- Communication protocol modifications
Changes affecting electrical or mechanical safety may require additional testing.
After the required evaluations are completed, the customer can confirm the battery design for production preparation.
Stage Output: Customer-approved battery specifications and design confirmation.
7. Stage Seven: Certification and Compliance Evaluation
Certification requirements should be identified during the initial project planning stage.
Depending on the battery application and target market, testing or certification may involve the following standards:
| Standard | Application or Purpose |
|---|---|
| UN38.3 | Lithium battery transportation testing |
| IEC 62133-2 | Safety requirements for portable sealed secondary lithium cells and batteries |
| IEC 62619 | Safety requirements for industrial secondary lithium cells and batteries |
| EN 50604-1 | Safety requirements for lithium-ion battery systems in applicable light electric vehicle applications |
| UL 2271 | Safety requirements for batteries used in light electric vehicle applications |
| IEC 60529 | Enclosure ingress protection classification |
The applicable requirements depend on product classification, destination market, equipment application, and certification scope.
Certification-related activities may include:
- Preparing test samples
- Technical documentation
- Laboratory evaluation
- Electrical safety testing
- Environmental testing
- Design modifications
- Retesting where required
Certification testing may take place during appropriate stages of product development, depending on the test plan and design maturity.
Stage Output: Required test documentation and certification results, where applicable.
8. Stage Eight: Pilot Production and Manufacturing Preparation
After the battery design is approved, the project may proceed to pilot production.
Pilot production is used to evaluate manufacturing processes and confirm the production documentation.
Production Material Preparation
The manufacturer confirms:
- Modell einer Batteriezelle
- BMS specifications
- Enclosure materials
- Steckverbinder
- Wiring harnesses
- Insulation materials
- Packaging materials
Production Process Preparation
Preparation may include:
- Assembly instructions
- Welding parameters
- BMS programming requirements
- Electrical inspection procedures
- Production fixtures
- Quality inspection criteria
- Packaging instructions
Pilot Production Evaluation
A pilot batch may be used to verify:
- Assembly sequence
- Component compatibility
- Elektrische Leistung
- Manufacturing process
- Inspektionsverfahren
- Produktkonsistenz
The pilot production quantity depends on the project scope and production requirements.
Stage Output: Verified manufacturing process and production documentation.
9. Stage Nine: Mass Production and Quality Control
After production approval, the project proceeds to mass manufacturing according to the confirmed order quantity and delivery schedule.
Battery Pack Production
The production process may include:
- Materialeingangskontrolle
- Battery cell grouping
- Zellanordnung
- Welding and electrical connections
- BMS-Installation
- Insulation assembly
- Enclosure assembly
- Elektrische Prüfungen
- Endkontrolle
- Verpackung
Production Quality Control
Quality control activities may include:
- Cell model verification
- Voltage inspection
- Connection inspection
- BMS protection verification
- Charging and discharging checks
- Communication testing where applicable
- Dimension inspection
- Überprüfung des Etiketts
Inspection requirements should be defined in the production quality plan.
Packaging and Shipping
Packaging and transportation arrangements depend on the battery specifications, destination, and applicable shipping regulations.
Customers should confirm:
- Order quantity
- Delivery address
- Shipping method
- Required transportation documents
- Verpackungsvorschriften
- Applicable Incoterms
Stage Output: Manufactured battery packs prepared for delivery according to the approved specifications.
10. What Factors Affect the Custom Battery Pack Development Timeline?
The development timeline depends on the technical scope and manufacturing requirements of each project.
| Factor | Potential Impact on Development Schedule |
|---|---|
| Battery cell availability | Procurement time and sample preparation |
| Customized BMS | Hardware development, firmware programming, testing |
| Enclosure design | Mechanical drawings, tooling, prototype production |
| Special connectors | Supplier procurement and interface validation |
| Kommunikationsprotokoll | Software integration and system testing |
| Zertifizierungsanforderungen | Laboratory scheduling, sample preparation, testing |
| Customer evaluation | Equipment integration, feedback, sample approval |
| Design changes | Drawing revisions, sample modifications, retesting |
| Production quantity | Material procurement and production scheduling |
Battery Cell Procurement
Cell availability depends on the selected brand, model, quantity, and supplier conditions.
If a project requires a specific cell model, procurement should be considered during development planning.
Customized BMS Development
Projects requiring new BMS hardware or firmware involve engineering design and functional verification.
Communication protocol integration may also require testing with the customer’s equipment.
Custom Enclosure Tooling
A new plastic injection mold or metal enclosure design may require tooling preparation and mechanical validation.
Customer Approval
The customer’s evaluation schedule is part of the overall project timeline.
Sample modifications and additional testing should be included in the project plan when required.
11. How to Plan a Custom Battery Pack Development Schedule
OEM customers can organize the project into defined milestones.
| Development Milestone | Required Confirmation |
|---|---|
| Requirement Review | Electrical and mechanical specifications |
| Technische Konzeption | Cell configuration, BMS, enclosure |
| Design Approval | Drawings, BOM, prototype requirements |
| Prototype Production | Sample quantity and manufacturing specifications |
| Musterprüfung | Electrical, mechanical, thermal and communication tests |
| Customer Evaluation | Equipment integration and sample feedback |
| Design Freeze | Approved specifications and revision status |
| Zertifizierung | Applicable standards and testing scope |
| Pilot Production | Manufacturing process and quality requirements |
| Massenproduktion | Order quantity, delivery and inspection requirements |
The time allocated to each milestone should be determined according to the confirmed project scope.
Some engineering, material procurement, and documentation activities may take place in parallel when the project conditions allow.
12. Information Required to Estimate Battery Development Lead Time
To prepare a development schedule, a battery manufacturer generally requires the following information:
1. Battery Specifications
Nominal voltage, capacity, cell chemistry, and charging voltage.
2. Current Requirements
Continuous discharge current, peak current, and peak duration.
3. Mechanical Requirements
Battery dimensions, mounting positions, enclosure material, and mechanical drawings.
4. BMS Requirements
Protection functions, CAN, UART, RS485, and temperature monitoring.
5. Connector Requirements
Charging, discharging, and communication connector models.
6. Environmental Requirements
Operating temperature, waterproof protection, vibration, and installation conditions.
7. Certification Requirements
Target market and applicable battery standards.
8. Sample Quantity
Number of prototype batteries required for evaluation.
9. Production Plan
Initial order quantity, expected production volume, and target delivery schedule.
Providing this information helps establish the engineering scope, material requirements, and development milestones.
13. Custom Battery Pack Development at Dongguan Yizhan Electronics Technology Co., Ltd.
Dongguan Yizhan Electronics Technology Co, Ltd., operating under the Erste Kraft brand, provides OEM and ODM custom lithium battery pack development and manufacturing services.
Our battery pack business covers electric mobility, robotics, industrial equipment, and energy storage applications.
Our customization scope includes:
- Ternary lithium-ion and LiFePO4 battery pack configurations
- Individuell angepasste Spannung und Kapazität
- Auswahl der Batteriezellen
- BMS hardware and software customization
- CAN, UART, and RS485 communication
- Customized plastic and aluminum enclosures
- Battery connector and wiring customization
- NTC temperature monitoring
- Battery pack assembly and testing
- Technical documentation and certification project support
For OEM battery projects, development activities may include technical requirement evaluation, electrical configuration, BMS development, mechanical design, prototype production, testing, and manufacturing preparation.
Project schedules are evaluated according to the confirmed specifications, component availability, development requirements, and production quantity.
Schlussfolgerung
The custom battery pack development timeline includes multiple stages, from technical requirement confirmation and engineering design to prototyping, testing, customer approval, and mass production.
Battery cell selection, BMS development, enclosure design, certification requirements, and customer evaluation can influence the development schedule.
For OEM and ODM projects, establishing technical specifications and project milestones during the initial development stage helps coordinate engineering activities, component procurement, prototype evaluation, and manufacturing preparation.
Whether you are developing an electric bicycle battery, AGV battery module, AMR battery system, service robot battery, or industrial battery pack, the development schedule should be based on the actual product requirements.
Planning a custom lithium battery pack project?
Kontakt Dongguan Yizhan Electronics Technology Co., Ltd. (First Power) with your battery specifications, mechanical drawings, BMS requirements, prototype quantity, and estimated production demand.
Our team can review your project requirements and discuss the technical development scope, prototype arrangements, and production planning.